Our County

Collage 13

 
Event:  Hagersville Resurfacing Project Update - August 14 
Type:  Information  
Department:  Public Works  
Division:  Engineering Services  
Open:  2017-06-06  
Close:  2017-08-30  
Reference Document:  Hagersville Resurfacing Project Update - August 14  
Notes: 

Project Update - August 14 

Work is starting on Main Street North. The work will include the following:

Main Street – Railway Street to Oneida Street 

- Installation and commissioning of temporary watermain

- Water service hookups to temporary watermain

- Cut and cap existing watermain

- Begin removal and replacement of existing watermain and services

- Replacement of existing sanitary laterals

- Restoration of road cuts with asphalt

This part of the project is anticipated to take four weeks to complete.

 

Work will also be occurring on other streets: 

Walpole Drive, Howard Street, Church St West, John Street

- Saw cutting of asphalt

- Concrete sidewalk and curb repairs/ replacements

- Minor repairs to storm sewers and catchbasins

- Milling of roadway surface

- Asphalt resurfacing

Union Gas is also working in Hagersville completing urgently required upgrades to their infrastructure. They have completed their upgrades on Main St North and have started their upgrades on Main St South. Coco Paving will be scheduling their project works to avoid any direct conflicts with work 

ACCESS:  

During construction every effort will be made to minimize impact to the local businesses and properties. Pedestrian access will be maintained generally at all times.  The Contractor will be installing signage to direct traffic and pedestrians.  However, there will be times when construction is occurring directly in front of your property that may result in a temporary, short term loss of access (e.g., pipe installation, sidewalk construction, etc.).  Again, every effort will be made to minimize loss of access and any impacts to businesses.  Emergency services will have access at all times. 

Haldimand County will post project updates every two weeks on our website and Facebook page. 

 

CONTACT INFORMATION:  

If you have any issues, questions or concerns, please contact the following:

Haldimand County 

Project Manager – Mike McGlynn King
905-318-5932 ext. 6408

Email: mking@haldimandcounty.on.ca

Contractor – Coco Paving  

Michael Luongo (Office) 905-679-1524 ext 3005

Alternate Contacts - Haldimand County  

Sue Flaherty – Administrative Assistant 905 318 5932 ext 6404

Tyson Haedrich – Director, Engineering Services 905 318 5932 ext 6437 

Interior Footer